The direction of the overlap is opposite to the direction of the prevailing winds.
Onduline roofing sheets overlap.
Of course sheets can be cut but there s a minimum requirement for overhang 70mm at the eaves and pitching 5 degrees.
Start fixing sheets at the opposite to prevailing winds end of the roof.
Nail or screw every corrugation on eaves overlaps and ridges.
Lay ridge elements with a minimum overlap of 12 5 cm.
Slope of the roof.
15 fixings minimum should be used per sheet.
The rise if the vertical distance of the ridge above the eave.
Fix 19 nails or screws per sheet to have a longlasting and guaranteed roof.
Get your measurements right.
Overlap 12 cm 3.
Ensure watertightness at ridge by applying the onduvilla foam fillers on both sides of the ridge line.
The slope of the roof can be calculated from measurements of the rise and run of the roof.
The roof slop is often stated as the inches of vertical rise per 12 inches of horizontal run length.
To have a long lasting and guaranteed roof it is mandatory to follow the nailing order and pattern ridges start fixing the ridge element opposite to the prevailing winds end of the roof.
Stagger the rows by starting the second row with a half sheet see in drawing the sheet 4.
Overlap and side overlap.
Up signs indicate the direction of the ridge to lay the sheets correctly.
Ensure waterproofing by aligning the overlapping lines.
Begin every second raw with a sheet cut in half vertically.
The ridge element should overlap the onduline sheet at minimum 14 cm.